Data center companies risk losing hundreds of millions in Texas grid deposits after Governor Greg Abbott's pause on new interconnection approvals left no resumption timeline.
"The rub here is that nobody knows how long this will be delayed," John Crossley, managing partner at corporate law firm K&L Gates, said.
Projects seeking entry to ERCOT's Batch Zero program were required to post $50,000 in security per megawatt of grid-connected capacity, according to law firm Butler Snow. Given the scale of announced projects, some companies have posted more than $100 million, most of which could become nonrefundable under a draft Public Utility Commission of Texas rule that would raise the nonrefundable share of deposits to 80 percent from 20 percent.
ERCOT is tracking more than 400,000 megawatts of proposed data center capacity seeking grid connections, more than four times the state's record peak load of about 91 gigawatts. The pause comes as Texas is forecast to surpass Virginia as the world's largest data center hub by 2030, and ahead of a September PUC meeting that could decide the deposit rule.
Abbott's directive, issued this week, requires audits of all planned data centers seeking grid connections, covering power demand, water use, tax incentives, ownership structures and local impact mitigation. The governor, who said the audit aimed to protect "Texans' safety and quality of life," did not disclose a timeline for completion. ERCOT said it would postpone the Batch Zero transmission planning study.
Multiple transactions, including land leases that underpin major data center projects, are contingent on approvals through the Batch Zero process, putting those deals in jeopardy. Data center businesses say they are seeking more guidance from the state, though there has not yet been a rush to cancel projects.
"It is still uncertain if a company may be financially better off pulling their project now before the September (Public Utility Commission of Texas) rule change, but that's not the norm," said Cameron Poursoltan, director of energy policy in Texas for the Data Center Coalition, a trade group with about 50 members.
The pause follows New York's one-year moratorium on large-scale data centers imposed in July, the first such statewide action, and rising local opposition across Texas. A June Reuters/Ipsos poll showed just one-third of Americans approve of the pace of data center construction.
The regulatory uncertainty creates an incentive for grid applicants to withdraw before the September rule change takes effect, potentially stalling billions in AI infrastructure investment in Texas. Investors will watch the PUC's September meeting for the final deposit rule and any timeline for resuming Batch Zero approvals.
This article is for informational purposes only and does not constitute investment advice.